UDOT update: Angel Street to be paved starting Oct. 23; Single lane closures planned later on I-15

Article Published 10/20/2017
On the I-15 Layton Midtown Crossing Project, work crews will begin paving portions of Angel Street, from Main Street to 1200 North, starting Monday, Oct. 23 – weather permitting. The new, revamped intersection at Angel Street and Main Street should be open by November.
The Layton Crossing road west of I-15 and east of Main Street will also be paved in the coming two weeks. 
Crews will also pour the columns in the I-15 median on Thursday, October 26 to Friday morning, October 27. Motorists can expect a single lane closure on I-15 southbound between 7 p.m. and 5 a.m., and a double lane closure on northbound I-15 between midnight and 5 a.m. of those days.
Work is also nearing completion on the new Main Street and Layton Crossing intersection.
-Contact the project team with any questions at 801-499-6577 or email laytoncrossing@utah.gov.