Update on 2 UDOT road projects in Layton

Article Published 06/01/2015

Road construction continues in Layton City.
The Utah Department of Transportation is still working on Antelope Drive and the Antelope Drive extension projects.
-The final layer of pavement on Antelope Drive, from University Park Boulevard to 2200 West, is scheduled to be poured the night of Monday, June 1, weather permitting.
Curb and gutter will also be completed along Robins Drive over the weekend.
-Beginning Saturday, June 6 through Monday, June 8, crews will place the final “seal coat” of asphalt  and the final striping throughout Antelope Drive Extension and US-89 Intersection project. While this is a fast moving operation, it will require temporary lane shifts and access closures during paving.